leaf bullet Building the Future, Restoring the Past

Phase 1 of Capital Project set to kick off this summer






Elementary school work - playground, athletic fields, parking - first to get upgrades

June 3, 2016

Superintendent Jon Peterson announced today that the first phase of the Building the Future, Restoring the Past" capital project - which includes work at the elementary school - has received approval from the state Education Department.

The district's architects for all three phases of project is BCK-IBI. MCS employees whose instructional or office spaces were impacted have been directly involved in the designs.

Phase 1 was submitted last month to the New York State Education Department and the school district received approval on June 2, said Peterson.

Phase I will include this work, all at the elementary school:

»  New playground complete with improved site drainage

»  Improved athletic fields- Baseball, soccer, softball

»  Improved site lighting

»  Improved parking

»  Potentially improved bus drop off

»  Improved sanitary piping and grease traps

 

Here is the Phase 1 timeline:

» 6/7/16 - Bid Opening

» 6/14/16 - Special Board of Education meeting to award bids

» 6/27/16 - Begin construction

 

The district is also heavily involved in Phase 2 and 3 design. Here is the timeline:

» 6/7/16 - Design of Athletic Fields and the auditorium

» 6/28/16 - Engineering Meeting II (HVAC, lighting, security, plumbing,etc)

» 9/16 - Submission to the state Education Deparment

Last month, the Board of Education interviewed and appointed C&S to provide construction management services to the district. They come highly recommended and are expected to ensure a high quality, on schedule and value added product, said Peterson.

Here's an overview of the project, which took more than a year to develop (PDF).

This newsletter about the project was mailed to the community (PDF).

Check out the webpage about the capital project.

 

¤¤¤¤¤